We use cookies to ensure our site functions properly and to store limited information about your usage. You may give or withdraw consent at any time.To find out more, read our privacy policy and cookie policy.
Manage Cookies
A cookie is information stored on your computer by a website you visit. Cookies often store your settings for a website, such as your preferred language or location. This allows the site to present you with information customized to fit your needs. As per the GDPR law, companies need to get your explicit approval to collect your data. Some of these cookies are ‘strictly necessary’ to provide the basic functions of the website and can not be turned off, while others if present, have the option of being turned off. Learn more about our Privacy and Cookie policies. These can be managed also from our cookie policy page.
Strictly necessary cookies(always on):
Necessary for enabling core functionality. The website cannot function properly without these cookies. This cannot be turned off. e.g. Sign in, Language
Analytics cookies:
Analytical cookies help us to analyse user behaviour, mainly to see if the users are able to find and act on things that they are looking for. They allow us to recognise and count the number of visitors and to see how visitors move around our website when they are using it. Tools used: Google Analytics
No analytics cookies have been enabled on this site. There are no cookies to review.
The project team has recently completed the 16-month design process for Ucluelet’s new Water Treatment Plant, which will be built at the existing Lost Shoe Creek aquifer well site. The new facility will remove iron and manganese from the water supply, addressing Ucluelet’s long-standing brown water issues. Construction will take place through the winter, with the plant expected to be operational by fall 2026.
Watch below to see how the Water Treatment Plant project was designed!
Background
Drinking water for the District of Ucluelet (DOU) is sourced from the Lost Shoe Creek Aquifer and pumped from three wells to the existing water treatment plant. Although the water is safe to drink, the raw water is high in iron, manganese, and turbidity and the additional of chlorine to provide necessary disinfection also causes the iron and manganese to precipitate out and settle in our water distribution system. This leads to discoloured (red/brown) water.
The Challenge
Ucluelet’s existing treatment processes and water quality do not meet current regulatory requirements as defined by the Guideline for Canadian Drinking Water Quality. Ucluelet’s post-treatment water is consistently testing higher in Manganese, Iron, and turbidity than the regulatory levels require. To address this challenge a new treatment process is required.
The Solution
Over the past several years the District has been working towards the implementation of a new water treatment system for our community. After the evaluation of various treatment options and testing of the proposed solution, a system was chosen that combines filtration, chlorine disinfection and ultraviolet (UV) inactivation to remove the iron, manganese, and turbidity from our source water. This solution also helps to provide capacity to serve the Districts 30-year growth projections.
The DoU also worked to secure grant funding for this new treatment system and was successful in obtaining approximately $7.04 Million through the Investing in Canada Infrastructure Program (ICIP).
Over the next year, a new prefabricated building will be constructed at the site of the existing WTP and all the treatment system equipment and supporting infrastructure will be installed.
Recent Project Updates
Detailed design of the new water treatment plant (WTP) was completed in September 2025, and a tender was posted for construction of the plant.
In September 2025 the construction contract was awarded to Ridgeline Mechanical Ltd.
As of November 2025, bulk excavation has commenced at the existing WTP site.
Schedule
Construction of the new treatment system is scheduled to be completed by the end of 2026. Some commissioning and treatment implementation activities may progress into early 2027.
Budget
In addition to the obtaining the ICIP grant funding, the District completed an alternative approval process for Loan Authorization Bylaw 1304, 2022, allowing for long-term borrowing of up to $13,000,000.
The current estimate project costs fall well within the total project budget, and are allocated as follows:
Design and Construction Contract Management
$1,405,600
Construction Costs
$11,353,079
Contingency
$1,275,868
Total Estimated Project Cost
$14,034,547
May 2026 Update
Foundation walls are complete and backfill is in progress along with underground piping. Building floor slab pour is schedule for mid May.
Building steel touch up painting scheduled for May. Building steel installation scheduled to commence in June.
Water Treatment Plant
The project team has recently completed the 16-month design process for Ucluelet’s new Water Treatment Plant, which will be built at the existing Lost Shoe Creek aquifer well site. The new facility will remove iron and manganese from the water supply, addressing Ucluelet’s long-standing brown water issues. Construction will take place through the winter, with the plant expected to be operational by fall 2026.
Watch below to see how the Water Treatment Plant project was designed!
Background
Drinking water for the District of Ucluelet (DOU) is sourced from the Lost Shoe Creek Aquifer and pumped from three wells to the existing water treatment plant. Although the water is safe to drink, the raw water is high in iron, manganese, and turbidity and the additional of chlorine to provide necessary disinfection also causes the iron and manganese to precipitate out and settle in our water distribution system. This leads to discoloured (red/brown) water.
The Challenge
Ucluelet’s existing treatment processes and water quality do not meet current regulatory requirements as defined by the Guideline for Canadian Drinking Water Quality. Ucluelet’s post-treatment water is consistently testing higher in Manganese, Iron, and turbidity than the regulatory levels require. To address this challenge a new treatment process is required.
The Solution
Over the past several years the District has been working towards the implementation of a new water treatment system for our community. After the evaluation of various treatment options and testing of the proposed solution, a system was chosen that combines filtration, chlorine disinfection and ultraviolet (UV) inactivation to remove the iron, manganese, and turbidity from our source water. This solution also helps to provide capacity to serve the Districts 30-year growth projections.
The DoU also worked to secure grant funding for this new treatment system and was successful in obtaining approximately $7.04 Million through the Investing in Canada Infrastructure Program (ICIP).
Over the next year, a new prefabricated building will be constructed at the site of the existing WTP and all the treatment system equipment and supporting infrastructure will be installed.
Recent Project Updates
Detailed design of the new water treatment plant (WTP) was completed in September 2025, and a tender was posted for construction of the plant.
In September 2025 the construction contract was awarded to Ridgeline Mechanical Ltd.
As of November 2025, bulk excavation has commenced at the existing WTP site.
Schedule
Construction of the new treatment system is scheduled to be completed by the end of 2026. Some commissioning and treatment implementation activities may progress into early 2027.
Budget
In addition to the obtaining the ICIP grant funding, the District completed an alternative approval process for Loan Authorization Bylaw 1304, 2022, allowing for long-term borrowing of up to $13,000,000.
The current estimate project costs fall well within the total project budget, and are allocated as follows:
Design and Construction Contract Management
$1,405,600
Construction Costs
$11,353,079
Contingency
$1,275,868
Total Estimated Project Cost
$14,034,547
May 2026 Update
Foundation walls are complete and backfill is in progress along with underground piping. Building floor slab pour is schedule for mid May.
Building steel touch up painting scheduled for May. Building steel installation scheduled to commence in June.